To date, the removal program has removed combustible cladding from MCG, a large hospital, 10 public housing buildings and 40 Victorian schools.

However, a significant number of cladding removal works remain unfinished. As of mid-2021, 723 buildings have been referred to statutory authorities, including 176 in the last fiscal year, and 536 have been included in the program, as reported by Kawra Guardian.

CSV claims that the removal program encountered a number of problems that resulted in significant unfinished work, including the elimination of cladding in professional compensation insurance, the reluctance of original manufacturers to return and modify combustible cladding, and the non-cladding building defects that caused removal and replacement. Tough

Dan O’Brien, chief executive of CSV, acknowledged that much remains to be done to complete the program, although an industry-first personal compensation insurance scheme has allowed more manufacturers to begin the process.

“We are facing a lot of complications,” O’Brien said, as reported by Kawra Guardian. “Over the next 12 months, the company will continue to refine its processes and procedures throughout 2020/21 as it seeks to modify further buildings across both residential and government programs through each of these issues.”

Read more: Victoria Cladding Insurance spent 7 million to close the gap

In February 2021, the Victorian government announced that it would spend $ 7 million on insurance to help builders and consultants repair more than 500 residential buildings marked with combustible cladding.

In an earlier statement, CSV confirmed that it has secured coverage within its $ 600 million budget, filling an insurance gap to help companies get cladding discount-free professional compensation cover during and after their work.

“We’re really looking at a program that has a lot of reliance on fire engineers, building surveyors, architects, [and] The first three, in particular, have significant limitations in their policies that make it very difficult to find a good market depth, “O’Brien told the Australian Financial Review (AFR) in February 2021.

Planning Minister Richard Winn added in an earlier statement that the lack of professional compensation insurance to cover cladding is an international problem. However, he claimed that the previous government was responsible for the privatization of building surveyors.

“We find ourselves in this situation because of the privatization of building inspectors under the former Liberal government,” Wayne told AFP.

.